Guidelines for the final beneficiaries

All the subprojects approved by the CEB/EIB are specified in the published Procurement Plan.

  1. For each subproject, a Co-Financing Agreement for Construction of Water Management Facilities and/or Preparation of Design Documents shall be concluded between the Final Beneficiary and Hrvatske vode.
  2. In addition to the Co-Financing Agreement, the Final Beneficiary shall complete the form „Subproject Information“ with information required by the Banks (technical, financial and other indicators). It shall include a map showing the location of the project and a plan showing the layout, indicating existing and proposed key water and wastewater infrastructure such as water mains, pumping stations, treatment plants, trunk sewers, etc.
  3. For each subproject, the following documents on the subproject’s compliance with nature protection and environmental protection regulations shall be submitted:
    • A certificate of the Ministry of Environmental and Nature Protection about compliance with nature protection requirements – Birds Directive (79/409/EEC) and Habitats Directive (92/43/EEC) (more details under Nature Protection)
    • An Environmental Impact Study, i.e. its Non-Technical Summary or a certificate of the competent authority that EIA is not required (more details under Environmental Protection)

Other documents – location and building permits and other documents – shall be submitted as requested by Hrvatske vode.